Link Securities | The company will continue its battle with the Madrid Regional Government over the M-203, a motorway between Vallecas and Alcalá de Henares that Ferrovial was awarded in 2005 but was never able to complete.

The Supreme Court (TS) has accepted for consideration the appeal lodged by the infrastructure group against the ruling issued by the High Court of Justice of Madrid (TSJM) in February 2025. In that ruling, the judge rejected Ferrovial’s claim for higher compensation following the termination of the contract for the construction and operation of the road. The main point of contention centres on the applicable interest.

In 2021, the Community of Madrid paid the M-203 concessionaire, owned by Ferrovial, €73.38 million in respect of the investment’s asset value (VPI) as a result of the termination of the works concession contract. This figure is a far cry from the nearly €250 million claimed by the company (€144 million for loss of profits).

About the Author

The Corner
The Corner has a team of on-the-ground reporters in capital cities ranging from New York to Beijing. Their stories are edited by the teams at the Spanish magazine Consejeros (for members of companies’ boards of directors) and at the stock market news site Consenso Del Mercado (market consensus). They have worked in economics and communication for over 25 years.